Archives For 834 S Monroe Renovation

It’s been four weeks since construction began.  We’re almost closed in.  Friday after Thanksgiving, and my family has the day off…as does our Contractor.  It’s a pleasant reprieve from the hectic push of project deadlines all trying to get bid before the holidays.

In the belly of the whale.  It’s a shame this will all be concealed by drywall.

WP_20141125_16_37_32_Pro

 

What comes down must go up.  Demolition.

WP_20141103_11_01_23_ProWP_20141103_15_32_17_ProWP_20141105_09_25_23_Pro

WP_20141103_13_09_34_ProWP_20141104_17_18_36_ProWP_20141104_17_17_04_Pro

Demolition took only a few days, but was the hardest to work through.  Especially the masonry gables coming down. My brain was completely frazzled by mid-afternoon. Having learned my lesson, I vacated to the public library on the day they brought down the chimney.  It can only go up from here.

 

Floor Joists.

WP_20141105_12_18_55_ProWP_20141107_13_19_35_Pro

WP_20141106_15_33_23_ProWP_20141107_13_20_36_Pro

 

The Roof.  Framing and Sheathing.

WP_20141113_12_25_13_ProWP_20141114_13_01_18_Pro

WP_20141118_15_25_39_ProWP_20141120_09_04_25_Pro

WP_20141110_16_32_30_ProWP_20141118_15_24_27_ProWP_20141124_16_12_26_Pro

WP_20141125_16_32_32_Pro

Advertisements

I’ve put off writing my first blog post, trying to decide what topic would be worth the start.  And finally, I have a reason to blog.  We’re beginning construction of a second floor addition at our 1939 house (read: home office).  As an independent spec writer, I work out of my home and travel to my architects’ offices for meetings.  We’ve moved ourselves into the basement over the last week or two.

And now today, Day One, I’m attempting to work through the noise, trying to gauge the intelligence of this decision.  Our cat Wrigley has a brain the size of a walnut, as I learned from some nature show.  I never knew if they meant with or without the shell, but based on my cat, it seems to vary day to day.  Today, he has a walnut-with-shell brain, and he’s even smarter than me – he’s hiding in the darkest reaches of our basement spare bedroom’s closet.  If I could fit in there with my laptop, I’d join him.

The Contractor’s work today consists of delivering a dumpster, laying OSB to protect the existing 1st level wood floors, taking down our wood doors, and taking the plaster ceilings down.  I said “laying” OSB, I should have said “dropping” OSB.  But that step is done, and now they are unscrewing the door hinges from the frames. There’s a lot of thumps, and the sounds of drilling and dragging.

Here’s a quick “before” picture from a couple days ago.  It’s already dated because as of five minutes ago, there’s now a dumpster in the driveway.  I’ll be tracking construction progress in future posts.  But today, I need to get back to my work – with some headphones.


Before – View from across the street.  Goodbye green grass.

WP_20141028_09_56_43_Pro__highres